Debt recovery

Court awarded RUB 1.08 million in unpaid fees for lift maintenance and repairs

ООО «Ритол» performed technical maintenance and repair of lifts for a management company. The work was confirmed by acts signed by the parties, but the customer did not pay in full. After a formal demand the debt was not settled voluntarily. Konsultant Law Firm represented the contractor in the commercial court. The court awarded RUB 1,077,311.80 in principal debt and RUB 50,888 in legal costs from the management company.

The management company accepted the work but did not settle in full

For several years ООО «Ритол» performed lift maintenance and repair work for ООО УК «Содружество-Сервис».

The parties had contracts for:

  • comprehensive technical maintenance of lifts;
  • routine repairs;
  • replacement and repair of lift equipment;
  • individual repair works.

The work was performed, handed over to the customer and documented in acts.

But payment was not received in full.

The cooperation began long before the court dispute

One of the main contracts for comprehensive technical maintenance and routine repair of lifts was concluded on 1 January 2017.

Under its terms, ООО «Ритол» performed technical maintenance and routine repair of lifts and the lift dispatch signalling system.

The customer was to pay for the completed work monthly on the basis of signed acts.

The contract provided for automatic renewal if neither party gave notice of its termination.

Acts were signed month after month

The case file contained a large volume of acceptance certificates for completed work.

In particular, under the main contract, acts were submitted for:

  • 2022;
  • 2023;
  • January — April 2024.

The total cost of the work under this array of acts was:

RUB 1,313,060.

Apart from regular maintenance, separate repair of equipment was performed

The cooperation was not limited to monthly technical maintenance.

ООО «Ритол» also performed individual works, including:

  • replacement of the lift cabin floor covering;
  • replacement of the cabin door drive;
  • other works on repair and replacement of lift equipment.

The performance of these works was also confirmed by signed acts.

The work continued under new contracts as well

In 2024 the parties concluded a new contract for comprehensive technical maintenance and routine repair of lifts.

The monthly cost of maintenance was:

RUB 46,895.

The work was performed from May to December 2024 and documented in the corresponding acts.

In January 2025 the maintenance continued under the next contract.

The customer paid, but did not settle in full

The management company repaid part of the debt

The case file confirmed that ООО УК «Содружество-Сервис» made individual payments to the contractor.

That is, real commercial relations existed between the parties:

the work was performed, accepted and partially paid for.

However, full payment was not made.

Before going to court, the client demanded voluntary settlement of the debt

On 13 February 2025 ООО «Ритол» sent a formal demand to the management company.

It proposed settling the existing debt under the contracts.

The demand was left without satisfaction.

After that, the matter had to be resolved in the Commercial Court of the Krasnoyarsk Territory (Арбитражный суд Красноярского края).

Key to the recovery

The work was confirmed by signed acts without objections

For the contractor, the documents confirming performance of the contracts were of fundamental importance.

Acceptance certificates for the completed work were submitted to the case file.

The court separately noted that they were:

signed by the parties without objections or remarks.

These documents confirmed that ООО «Ритол» had performed the work.

Work accepted by the customer must be paid for

After the work is performed and accepted, the customer has an obligation to pay for it in accordance with the terms of the contract.

In this case the customer signed the acceptance certificates for the completed work.

No evidence of full payment of their cost was submitted to the case file.

The court concluded that the management company had a counter-obligation to pay for the properly performed work.

According to the contractor’s calculation, the debt was even higher

Taking into account the partial payments made by the defendant, the calculation of ООО «Ритол» showed a debt of:

RUB 1,569,956.80.

However, when the claims were refined, the claimant itself reduced the amount it asked the court to recover to:

RUB 1,077,311.80.

Only the amount the client left in the claims could be recovered

After the claim was refined, ООО «Ритол» asked to recover:

RUB 1,077,311.80.

The court separately noted that the claimant independently determines the scope of the material rights it asks to protect.

The court therefore could not go beyond the claim as stated.

A separate part of the claims

The client withdrew the claim for RUB 372,996.60 in penalty

The claimant withdrew the RUB 372,996.60 penalty claim, and the court terminated the proceedings concerning that claim.

The defendant did not provide evidence that the outstanding balance had been paid

The court found proven the fact that ООО «Ритол» had performed the work.

At the same time, the defendant did not present evidence of payment for the completed work in the amount claimed.

Taking into account the signed acts and the absence of evidence of payment, the court found the claim for recovery of:

RUB 1,077,311.80

justified.

Result

RUB 1,077,311.80

The court awarded RUB 1,077,311.80 in principal debt from the management company

The Commercial Court of the Krasnoyarsk Territory ordered Sodruzhestvo-Servis Management Company LLC (ООО УК «Содружество-Сервис») to pay Ritol LLC (ООО «Ритол»):

  • RUB 1,077,311.80 — principal debt;
  • RUB 50,888 — reimbursement of the court fee.

Total awarded against the defendant: RUB 1,128,199.80.

The court awarded reimbursement of part of the court fee and ordered a separate refund from the federal budget

The court ordered the defendant to reimburse RUB 50,888 of the claimant’s court fee.

It also ordered a refund of RUB 27,115 in court fees from the federal budget.

This refund was separate from the RUB 1,128,199.80 awarded against the defendant.

For the recovery of a B2B debt, not only the amount matters, but also the system of documents

This dispute shows a classic situation of commercial debt.

The contractor performed work for a long time.

The customer:

  • signed the acts;
  • accepted the result;
  • made partial payments;

but did not settle in full.

For a court recovery, it was important to confirm:

the contractual relationship;

the actual performance of the work;

its acceptance by the customer;

the cost;

the payments made;

the remaining amount of the debt.

As a result, the stated principal debt of RUB 1,077,311.80 was awarded in full.

Our role

Konsultant Law Firm represented ООО «Ремонт и техническое обслуживание лифтов» («Ритол») — the claimant in the case.

The case was handled on the firm’s side by lawyer Viktor Erofeev.

During the dispute, the contractual relationship of the parties, the performance and acceptance of the work, the signed acts, the partial payments and the amount of the remaining debt were confirmed.

The court awarded in favor of the client RUB 1,077,311.80 in principal debt and RUB 50,888 in legal costs.

Case

No. A33-9438/2025

Court

Commercial Court of the Krasnoyarsk Territory (Арбитражный суд Красноярского края)

Operative part

26 June 2025

Decision in full

8 July 2025

Claimant

ООО «Ремонт и техническое обслуживание лифтов» («Ритол»)

Defendant

ООО «Управляющая компания «Содружество-Сервис»

Client’s role

claimant

Subject of the dispute

recovery of debt for completed works and services

Debt calculation before the reduction of the claims

RUB 1,569,956.80

Principal debt stated after refinement

RUB 1,077,311.80

Principal debt awarded

RUB 1,077,311.80

Penalty

RUB 372,996.60 — the claimant withdrew the claim, the proceedings were terminated

Court fee reimbursement awarded against the defendant

RUB 50,888

Total awarded from the defendant

RUB 1,128,199.80

Refund of the court fee ordered from the federal budget

RUB 27,115

Result

the claim for recovery of the principal debt was granted in the stated amount

Lawyer on the case

Viktor Erofeev, Konsultant Law Firm

Practice Areas

Practices Related to This Case

Nikolay Nemkov

Managing Partner, Konsultant Law Firm

Nikolay Nemkov

← All Cases

Have your completed works not been paid for?

We will check the contracts, acts, invoices, payments, correspondence and pre-litigation documents. We will determine the amount of the confirmed debt and the prospects of recovering it from the customer through the commercial court.